Total | - The Plaintiffs in claim used the same purchaurchase price Defendant used i.e., £125,000 for the line. But the Plaintiff was
concerned that the equipment had been working hard for Unilever, and it said it could not be confident that the equipment would be
up to the standard of its own. This was not proved by the Plaintiff. Such a thing required to be proved though evidence, before claiming
for refurbishment.
- By the same token one could argue that since the plant was decommissioned to scale down the operations in Prague, it would not have
used to its optimal level and the components were manufactured in 1980's and was in a better condition than the Plaintiffs, but there
was no evidence to support such contention, too. There are conjectures, without sufficient proof at the hearing.
- The Plaintiffs calculated its claim by asking Marchant to provide a quotation for refurbishment of the line to the extent that it
would include a warranty. The refurbishing price was as high as the second had plant value, indicating the extent of refurbishment.
Its price was £250,000.
- This comes with a warranty and there was no evidence that Plaintiff's machinery in the destroyed soap line had any warranty at the
time of destruction. So, obtaining machinery with warranty for the toilet soap line that did not have warranty was a 'bonus' for
the Plaintiff.
- The Plaintiffs' toilet soap line was destroyed comprising with mainly from MM components made in 1969.
- So the refurbishment of the toilet soap line was a substantial improvement to the soap line that can be considered as comparable
and this refurbished value cannot be considered as indemnity value. This was a 'bonus' for the Plaintiff and cannot be allowed under
indemnity value.
- The Marchants quote is to be found at Defendants Exhibit 5 at page 71 and says:
"However it was also proposed that you would take these machines in a fully refurbished state since to take them as they are as this moment all be it in good running condition they would carry no guarantees with the sale. By having them fully reconditioned you will receive the benefit of a full guarantee for the equipment.
The above is a general outline of our proposal and it should be well noted that the original quotation allowed for the equipment
to be supplied in an "as running" order un-reconditioned without guarantee and the revised quotation for the equipment to be refurbished
carries our full manufacturers guarantee".(emphasis added)
- Although no evidence was called by the Plaintiff as to what the quotation by Marchants entailed, it was clear from the costing of
the quotation that Marchants were quoting for a complete overhaul of all important components of the line. Mr. Godfrey in evidence
identified this as 'complete refurbishment with guarantee'. This was never a feature of the destroyed soap line.
Depreciation Method (Suggested as an Alternative by the Plaintiff)
- The Plaintiff suggested an alternative approach to establishing an indemnity value. It sought to establish the indemnity value of
the toilet soap line using the depreciated replacement value method. Though this method can be used for certain assets in the calculation
of the indemnity value, this was not suitable for the Toilet Soap Line destroyed by fire.
- Mr. Godfrey in his evidence explained why the depreciated replacement value method was inappropriate to establish indemnity for this
particular item. He said it was inappropriate because claim preparer used a new plant with brand new technology to derive a value
for an old plant of low technology. One cannot assume the 1969 technology to remain unchanged for more than three decades.
- Thus, the starting figure for depreciated model was not for a similar item to the one that was destroyed, but one with all current
technological advances and efficiencies that simply did not exist in the destroyed toilet soap line. This alone would be sufficient
to reject depreciated replacement method for the destroyed soap line.
- It should not be taken as rejection of depreciated replacement method for arriving at indemnity value, rather this method was not
suitable for the indemnity value ascertainment for this claim, under the given circumstances.
- The Plaintiff discounted 75% but provided no basis to support this rate of depreciation. It is often in accounting there are fixed
depreciating factors for different types of assets for different purposes. Sometimes, for tax purposes a different depreciating factor
would be applied, depending on the fiscal priorities of a country at a particular year. At the same time accounting standards would
also denote depreciating factors in order not to obtain inflated account statements. It may be important to depict the correct statement
of affairs from the financial statements. Either way these depreciating factors (percentages) will not be always same and will change
with time. So it is important to use an accepted depreciating method and calculate it and arrive at a value, which was not done in
this instance. So, there was no justification for deciding 75% depreciating factor.
- So 75% depreciation of the cost of new plant will not indicate indemnity value for the destroyed plant. This value cannot be even
used as any comparison since the starting point and depreciation factor (75%) were not justified for the lost item. So such a value
obtained cannot be utilized for any worthwhile comparison to determine indemnity value.
- Apart from this it was inappropriate to take a new machine and discount it when there was a comparable toilet soap line for sale at
that time, where even the two Directors thought fit to visit Prague for examining of that soap line. The fact that it was sold shortly
after the inspection by the Plaintiffs, proved the value of that comparable soap line in Europe. There was no evidence that the Plaintiffs'
plant that got destroyed had such a market value either in Fiji or in the region.
- So the toilet soap line which was on sale at Prague, was available to ascertain on a market tested basis the indemnity value of the
destroyed Plaintiff's plant. There was no evidence against the comparison of the two plants. According to the Plaintiff, the only
thing, required to make it be used as a comparable to the one destroyed was to obtain a warranty for said machinery. So, there was
no need to obtain the value of new machinery for calculation of the indemnity value of the said soap line.
- The Defendants could not be expected to find identical soap line as such a line would not exist or would be rare considering the age
of the MM components and also the different makes of components, that made toilet soap line that got destroyed from fire. At the
same time even if such a plant was located, whether the owners would be willing to sell or quote a price was another issue considering
the competition in the field. The Defendants have done what was possible to obtain a toilet soap line comparable to the one that
destroyed and by conduct the Plaintiffs admitted said soap line as comparable one to the destroyed one.
- The Plaintiff suggested that the $250,000.00 risk contingency allowed by Godfreys was allocated as a contingency only against the
Secondary Podder MM 1/250 s/N0 0769 C/W Screw feeder in Schedule M2, page 11 of 20 in Tab 11 in Folder 2.
- It was never part of the Plaintiff's case that the FJ$250,000.00 risk contingency was allowed against a specific item only. Mr. Faire
was not asked whether it was his position or understanding that the FJ$250,000.00 risk contingency was only for the Secondary Plodder.
- It would be improbable to suggest such a proposition, considering the amount allowed for the contingency. If there was a reason for
allowing such a value for contingency for one item only, there should be a basis for that and that basis should support documentary
evidence. Specially the correspondence between the parties.
- It was also clear from the communications of Mr. Godfrey prior to the litigation and even during evidence including the tables and
schedules prepared by both parties and presented to the court.
- The Plaintiff's own schedule at Tab 11, Schedule M2, page 11 of 20, the FJ$250,000.00 was a separate item altogether at the end of
the costing for the toilet soap line. If the Plaintiff had believed that the FJ$250,000.00 was a contingency only for the Secondary
Plodder, then Mr. Faire's schedules would have shown this only under the said item and the reason for such allocation would have
been stated.
- In 1999, the Plaintiff had the toilet soap plant valued at $875,532.00 (i.e Beca valuation). This evidence was at Folder 2, Tab 11,
Schedule M2 page 12 of 20 at line GF N.32. Four years later, the Plaintiff was claiming an indemnity value of $1,424,235.00 for the
same toilet soap plant. If such increase was justified it can be considered. Any plant and machinery would need to be depreciated
and cannot increase the price unless there were details of improvements to it with necessary adjustments to the said improvements.
- If the Plaintiffs desired a depreciation method to arrive at a price this price of $878,532.00 should have been the starting value
as that was the nearest valuation that was done before the fire. This value should be depreciated for five years and any additions
and improvements could be appropriately added for correction. This was not done and no explanation given for not using this valuation
by the Plaintiff. This can be considered as alternative method more accurate than obtaining the starting value from a brand new machine
with latest improvements and automation. In fact there was no need to search for such value when valuation of entire toilet soap
line was available as at 1999. So, if the depreciation method was to be used that value should be the starting value with adjustments,
like any improvements or replacements.
- Though using a different method the Defendant's calculation of FJD 855,764 was not only more realistic but can be considered as indemnity
value for the soap line in the assessment of damages in this proceeding, from the evidence presented to the court.
Laundry Soap Line
- The Laundry soap line comprised primarily of a plodder and vacuum hopper, pipe work, dossing pumps and lines and a soap cutter.
- The presented, adjusted and the amount in dispute for the Laundry Soap Line claim were as follows:
Presented | Adjusted | Dispute | $318,534.00 ($250,000 for repairs quoted by MM + $58,534 for the soap cutter) | $237,019.00 | $81,515.00 | - It was agreed between the parties that the laundry soap line, with the exception of the soap cutter, was repairable. The items were
located in an area least affected by the fire. This was accepted by both parties at the hearing. So in the evidence it was admitted
that these items could be repaired except the soap cutter. The repair costing was done by Mr. Wakelin for the Defendant and he gave
evidence. It was not clear who did the costing for the Plaintiff. It was not been done by Mr. Fair who gave evidence relating to
the said claim, he could not give details about the claim. So, the Plaintiff failed to prove their claim for Laundry Soap Line.
- The Defendant's argument in respect of this aspect of the claim was that the Plaintiff adduced no evidence to establish it claim for
$318,534.00. The Plaintiff only called Mr. Faire to give evidence on this aspect of its claim and this was not sufficient proof of
their claim. No evidence of quotation of soap cutter was presented to prove the allocation of $58,534 for the said soap cutter or
for the repair cost $250,000.
- First the Plaintiff should have proved the age and model of the soap cutter, that destroyed from the fire, to ascertain its indemnity
value. Without that how could the value of $58,000 be proved for the item for indemnity value. The Plaintiff did not make an effort
to prove such details to support their claim. Such details were not revealed in the evidence.
- In his evidence in chief, Mr. Faire said,( Folder 2, Tab 11 at page 7):
"Based on Punjas' verbal advice from MM on the potential scope and cost of repairs, we believe that $250,000.00 would be reasonable indemnification for this part of the
claim. This is at the lower end of the scale provided to us, the upper end being in the region of $350,000.00."(emphasis is mine)
- Mr. Faire then read from Folder 2, Tab 8 at page 13, paragraphs 42 to 46 relating to the Laundry Soap Line. At paragraphs 44 to 46
of Tab 8 Mr. Faire said:
44. "This line was specialized MM equipment that was badly damaged in the fire. Rajesh and Pravish Punja reported that discussions
with MM indicated that repairs were likely to be more extensive and complex that NIA's consultants had suggested and that they should
be executed by or at least overseen by a technical representative from MM, the manufacturer of the equipment.
45. On this basis, the Plant and contents claim for repairs to the Laundry Soap Line to restore it to the condition it was in immediately
before the fire was assessed at $318,534.00, which is $143,823.00 more than has been agreed by NIA.
46. The Punja claim also includes $58,911.00 for an MM Soap Cutter for which NIA has allowed an uncorroborated amount of $40,244.00
that I cannot explain. I have received no information in support of the lesser amount. I refer to the MD Final Report and the text
commencing "MM Soap Cutter" on page 7 for an explanation of the basis of the estimated repair cost of $58,911.00 salvage."
- This was the evidence adduced by the Plaintiff for its claim for the laundry soap line for $318,534.00. The amount claimed was no
more than a round off figure that MM apparently advised the Plaintiff it would cost to restore the laundry soap line to the condition
it was in immediately before the fire, but this evidence was not substantiated with documentary proof.
- There was no quotation by MM for the said repair and what type of repair that was intended for that price was not presented and to
what extent such repair was justified was not presented to the court. Whether such repair would include a warranty or not (as Merchants
have done in refurbishment to Toilet Soap Line) was not clear. In the circumstances the Plaintiffs have failed to prove their claim
for $318,534.00 as an indemnity cost of laundry soap line damaged by the fire.
- The Plaintiff did not assess or have anyone asses the repair costs for the repair of the laundry soap line. The items of repair and
extent of damage should be determined before quoting a figure for the repair. Without such an assessment a repair cost cannot be
determined. Mr Fair was unable to establish this claim in his evidence.
- Mr. Wakelin, who was an Engineer by profession in his evidence demonstrated in a detail how he arrived at price for the laundry soap
line identifying the damage and the required repair. Therefore the Defendant's adjusted figure of $237,019.00 was proved as indemnity
loss for the Laundry Soap Line. In the cross examination he was able to substantiate his position, with details of it.
- Though Mr. Faire said this Laundry Soap Line was specialized he could not prove how specialize it through evidence the amount claimed
by the Plaintiff. In the cross examination he said he could not substantiate the amount as he was not an Engineer. No Engineer was called by the Plaintiff
to substantiate this amount. The burden of proof of the claim was with the Plaintiff to prove the claim on balance of probability.
- The Defendant was able to explain in detail how the adjusted amount of $237,019.00 was arrived at. The repair cost of the Laundry
Soap Line was calculated with the assistance of Mr. Wakelin.
- The Defendant established the total cost of $237,019 by detailed measure of component costs, labour costs, expert engineer costs and
margins where applicable. Mr. Wakelin gave detailed evidence. He presented the detailed schedule of how the laundry soap line claim
was adjusted at $237,019.00. The Plaintiffs' contention that this was not proved is without merit.
- The evidence was to be found at the pages referred to in Defendant's Exhibit 5 and it was made up as follows:
Laundry Soap Adjustment | | (Summarised version of pages 113-115 of Defendant's Exhibit D5) | | Location | Description ( From Beca Valuation) | Adjustment | GF D.1 | BAR SOAP MANUFACTURING AREA | < | GF D.2 | Condg unit, MM, SC10TX, pipework, controls | inc inc | GF D.3 | Electrical power switch and control panel and cable | inc | GF D.4 | Jacketed pan, wrns steam heated 9500 mm dia | inc | GF D.5 | Second tank, 500dia, 600 high, mounted | inc | GF D.6 | Plodder MM TR227SE S/No. 2870 (refer below) | 199,836 | GF D.7 | Extruder head | inc | GF D.8 | Staging and steps to vacuum unit above plodder | inc | GF D.9 | Vacuum unit adj plodder (inc in Beca 255) | inc | GF D.10 | Tool stand adjacent plodder | inc | GF D.11 | Pumpset with balance tank, pipework | inc | GF D.12 | Vacuum pumpset. (inc above) | inc | GF D.13 | Vacuum pumpset, MM PL52200M c/w Seperator water tank | inc | GF D.14 | Pumpset MM 50mm c/w pipework & controls | inc | GF D.16 | Soap cutter, MM TCS continuous, roller conveyer - allowance | 30,000 | GF D.17 | Conveyor inc in Bca 258 | inc | GF D.18 | MM Colour additive Tanks 2 x 85 litre Twin head dosing pump | inc | GF D.19 | Twin head dosing pump inc in Bca 259 | inc | GF D.20 | Yellow colour additive tank as above | inc | GF D.21 | 20mm galv piping, additives to plodder | inc | GF D.22 | Cooling tank adj, 600l, 300w, 400h | inc | GF D.23 | Steam pipework and valves on dividing wall to toilet soap | inc | GF D.25 | Galv packing table, 650 sq x 300, | 8 | GF D.26 | 40 cm fan | 13 | GF D.27 | Crown hand pallet truck, | 250 | GF D.29 | 2no, 3 blade ceiling fans | 83 | GF D.30 | Switchboard | inc | GF D.31 | Fire hose reel- hose missing | 6 | GF D.32 | Soap bins x 33 | 1,989 | GF D.33 | Electric fly killer | 167 | GF D.34 | Metal shelving, AC type | 4,667 | |
| 237,019 | >Particulars of Item GF D.6 included above | | (Summarised version of Page 89 of Defendant's Exhibit D5) | | Plant item no | Item | | align"> op"> D2 | Heat exchanger (detailed calcul P90, D5) | 954 | D4 | Jacketed pan | 100 | D5 | Jacketed pan | 100 | D6 | Vacuum drier and plodder dust arrestors, barometric condenser (detailed calculation P90, D5) | 21,882 | D8 | Steps | 100 | D11 | Pump set /balance tank | 100 | D16 | Soap Cutter | 173,800 | D17 | Conveyor | 800 | D18 | Colour additive tanks (2No) | 1,800 | D20 | Yellow dosing tank | 1,800 | D26 | 40 cm fan | 200 | | Part total | 201,636 | | Less Less duplicated dosing tank | - 1,800 | | Subtotal carried to main adjustment 199,836 | < - Mr. Wakelin in evidence said that the Soap Cutter (Item D16 of his schedule in evidence W0010) was costed on MM's price at EU79,000
converted at EU 1:FJD2.00, plus 10% freight, bringing the total to $173,800 - Defendant's Exhibit D5 at page 90, item D15.
- From the available evidence for assessment of indemnity value for the laundry soap line that was damaged the Plaintiff had failed
to prove their claim. Mr. Fair was unable to prove the components in their claim. In any event he could not have proved them as he
often said he was not an engineer to answer issues relating to machinery. So on the balance of probability the amount $237,019.00
can be considered as the indemnity value for the loss to the Plaintiffs for the Laundry soap Line.
Other Areas
- The Plaintiff presented a claim for $163,614.00.Godfreys adjusted this claim at $147,844.00. The parties agreed to split the difference
at $155,729.There was no dispute on the amount of $155,729.
Consumable Stocks
- The Plaintiff presented a claim for $16,797.00. Godfreys accepted the claim of $16,797.00 for this item. There was no dispute for
the amount of $16,797.00.
Item 7 – Demolition
- The Plaintiff submitted a claim for $50,000 for demolition works.
- The presented, adjusted and disputed amount for the demolition works claim was as follows:
Presented | Adjusted | Dispute | $50,000.00 | $31,111.00 | $18,889.00 | - The Plaintiff could not substantiate the claim for $50,000. At one instance Mr. Fair said that he thought it was agreed. This cannot
be accepted as he could not produce any evidence to that effect.
- The Plaintiff had obtained 3 quotations for the demolition works but the quotations were not produced in evidence by the Plaintiff.
The Defendant's position was that Godfreys agreed to accept the lowest quotation obtained by Fawcett Faire for the demolition works.
This was corroborated by Defendant's Exhibit 2. This was an email from Mr. Moonlight of Godfreys to Mr. Maritz of Fawcett Faire confirming
the agreement. The relevant part of the email says as follows:
Hi David,
Confirming our conversation today, understand that the demolition quotes are now:
Goundra $56,000.00
CR $55,000.00
Construction $35,000.00 All VIP
The demolition quotes of all 3 contractors include the following:
- The ENTIRE building including slabs and foundations.
- The salvaged plants will be removed and transferred to the adjacent site.
- All inbuilt services will be demolished and removed unless advised otherwise.
- The demolition contract will be supervised by Sanjay Kaba.
Confirming we will not question the lowest quote (subject to seeing a hardcopy), and to Mark being able to see the associated plans
tomorrow to confirm they match with what is stated on the quotes.
- There was an agreement between Mr. Moonlight and Mr. Maritz that the lowest quote would be accepted by Godfreys. This was subsequently
confirmed by Mr. Moonlight when he said "Confirming we will not question the lowest quote." The lowest quote obtained by Fawcett
Faire was $35,000 inclusive of VAT. Excluding the VAT amount from the lowest quote of $35,000 was $31,111 and this can be considered
as the demolition cost.
General Contingency
Claim | Adjusted | nil | $30,000.00 | - Separate from other plant items Godfreys allowed a contingency of $30,000 for unknown costs associated with unidentified loss in the
plant area. This was included to allow for general items that may have been missed in the detailed assessment. The insured had no
corresponding item in its claim. Mr. Goffreys in evidence said that this amount was allowed considering nature of destruction where
parties might fail to identify all the claims. I allow this contingency.
Professional fees
Claim | Adjusted | Disputed credit amount | $149,807.00 | $153,325.00 | $3518 | The adjusted figure was more than the claim, so I cannot see any objection from the Plaintiff for paying more! I accept the adjusted
figure $153,325 for the said claim.
Europe trip
- The Defendant agreed to pay for part of the expenses for two Punja Directors to inspect the Prague Plant. There was no dispute for
this claim of 30,000. I allow it
MM Trip
- There is no dispute as the claim in this amount, too. The claim of 30,000 was agreed between the parties. I allow the claimed amount
of $30,000 for the said claim
Computer Allowance
- This claim was referred to items deducted from Item 1 – Office/Laboratory.
- The presented, adjusted and disputed amount for the computer allowance is as follows:
Presented | Adjusted |
| $0 | $15,500.00 |
| - It was separately estimated by Godfreys as the indemnity value of the computer system lost in the fire at $15,500, and the items to
which it related to office laboratory and plant claim were deducted by Godfreys from that category. Now the said category was undisputed
so the 15,500 should be allowed for computer allowance.
Item 13 – Salvage
- Mr. Godfreys credited a sum of $30,000 for salvage.
- The salvage provision of the Insurance Policy is found at Tab 7, page 8 – says:
Where any Insured property is lost or damaged, the company may:
(a) enter any building where the loss or damage has occurred and take and keep possession of the damaged property, (b) deal with the salvage in any reasonable manner; provided that –
- the Insured will not be entitled to abandon any property to the Company;
- the Company will not be entitled to sell or otherwise dispose of salvaged branded goods without the prior consent of the Insured.
- The Plaintiff in the written submission contended that the claim for salvage had to be determined by common law.(see paragraph 47)
This was not correct position, as it was specifically dealt in the Insurance Policy. Accordingly, the Defendant should deal with
salvage reasonably. This left the court to determine what was reasonable under the circumstances. Mr. Godfrey said the reason for
leaving the salvage with the Plaintiff. He said that the industry feared the salvage getting to the wrong hands – the competitors.
- Quite opposite to what contended by the Plaintiff, it was the Plaintiffs who cannot abandon any salvage property to the Defendant.
This was understandable as when something gets destroyed it may sometime become hazardous for the environs, and the primary obligation
in such situation would be the owner not the insurance company, but depending on the policy the cost of cleaning may be recoverable.
Even for sale of salvage the consent of the owner was needed, under the Insurance Policy.
- The Defendant was unable to provide evidence in support of the salvage value. There was no proof of that by the Defendant. This was
an item which the Defendant wanted to deduct from the claim, so the burden of proof was with the Defendant to prove the salvage value,
but it had not done so. Except Mr. Godfrey's evidence no quotation for salvage was produced at the hearing. This was inadequate to
prove salvage on the balance of probability. Even if there was a value for the salvage, it should be properly obtained from a person
interested in purchasing it and should include the details of the pricing including the manner of pricing the salvage.
- The Plaintiff argued that it had offered the salvageable items to the Defendant. Mr. Mr. Godfrey declined, saying it was for the insured
to proceed and secure best salvage for the material. This is not the correct position in terms of the conditions of the Insurance
Policy. In terms of the Insurance Policy the Defendant should obtain consent from the Plaintiffs if they desired to sell the salvage
to outside. Mr. Godfrey said this type of salvage was not sold to outside due to the stiff competition in the soap industry. This
evidence was not challenged in the cross-examination. So it is unlikely that the Plaintiffs would have given consent to the Defendant
to sell. If they desired the Defendant to sell then there should be evidence of their consent to such sale. There was none.
- The absence of that indicates that there was no such request from the Plaintiffs to the Defendant to sell the salvage in local market.
- Mr. Godfrey in his evidence also stated that there were few local interests shown for the salvage but did not sell due to the nature
of the soap industry where there was stiff competition. This evidence was not denied by the Plaintiffs, but the issue remained the
proof of the assessment of salvage . The Defendant was unable to prove $30,000 which they claim (for credit). There was no proof
of that amount at the hearing so it needs to be disallowed.
Claim for All services except Electrical
- The all services except electrical claim related to the pipes, pumps, valves, and related services. The presented, adjusted and the
amount in dispute All Services Except Electrical was as follows:
Presented | Adjusted | Dispute | $317,677.00 | $253,327.00 | $64,350.00 | Electrical Services
- The electrical services claim related to the cost of providing electrical services to entire plant.
- The presented, adjusted and the amount in dispute Electrical Services claim is as follows:
Presented | Adjusted | Dispute | $397,875 | $132,660 | $265,215 | - Above two claims were inter related and both were considered together.
- Mr. Faire was not able to explain how his presented claim of $317,677.00 for all services except electrical and his presented claim
of $397,875.00 for electrical services was made up. He said he did not bring the documents to support the claim.
- The Plaintiff also called Mr. Kumar, and Electrical Engineer, but he also said he did not bring the documents to support this assessment
which was the basis for the Plaintiffs' claim. They were the only witnesses that were called to prove the claim, but both have failed
to produce vital documentation to court to prove the claim, but the Plaintiff state that they have proved their claim. The total
claim for this item was substantial but none of them treated with the gravity of the claim.
- Similarly, Mr. Faire was not able to give any explanations for the claimed figure of $397,875 for the electrical services claim. In
particular, the sole document produced by the Plaintiffs in support of the services quantum, the EPL letter dated 13 June, 2003 was
shown to Mr. Faire. He was unable to identify the document or how it related to the plaintiff's claim.
- The Plaintiff called Mr. Kumar to give evidence on this claim. Mr. Kumar was a person having experience in factory layouts, supervision
of plant installation and plant commissioning, but his evidence was that he had left vital documents that support the claim in his
archive.
- The Plaintiff's claim for electrical services and all services except electrical formed a substantial part of its claim. The total
claim by the Plaintiff for these two items was $715,552.00.
- Mr. Kumar was not able to give details of his calculations of the figures. He did not present the details to support his costing for
the two items. Mr. Kumar's position was that he had prepared detail costing but they were back in his office in archives and he could
not bring them because of short notice by the Plaintiffs.
- The Plaintiffs had more than one year from the decision of the liability to prepare for the assessment hearing. This action was instituted
in 2005 and initially it was not decided to have a split trial, hence the necessary witnesses should have been arranged and with
necessary documentation at that time the documents that needed for proof should have been included in the affidavit verifying lists
of documents of the Plaintiff. The documents relating to the said calculation were not presented.
- Mr. Kumar was not able to give any details of his calculations for indemnity cost, except for his round figures in Tab 19 in Folder
2. It was for the Plaintiff to establish the extent of its loss. Mr. Kumar admitted that his costing details were never sent to the
Plaintiffs indicating that they were not even presented to respective parties, to this hearing. Though it may not be a factor that
I needed to consider for the assessment of indemnity costing this indicate that, the basis for these rounded off figures were not
seen even by the Plaintiffs!
- So, how could they rely on such report for assessment before a court of law for proof on balance of probability. Mr Fair had totally
relied on Mr. Kumar's assessment, but it was clear that even he would not have been convinced about the manner in which this claim
was presented in the claim preparation. So how could he satisfy the civil burden of proof in court? This was not a proof on balance
of probability the indemnity cost of the said items.
- The fact that Mr. Kumar admitted that he did not provide the details of his costing to the Plaintiff and this was consistent with
the evidence of Mr. Wakelin at Exhibit 8, paragraphs 20 and 22, where he said that details of the Plaintiff's costing were not made
available to him at any time of the claim preparation and adjustment process.
- Mr. Godfrey in his evidence stated that the claim relating to electrical services and all services except electrical was one of the
most detailed areas of Godfreys assessment, and relied on a complex series of unit costs extrapolated to measure the insured's exact
requirements for this plant. He had calculated details of bracket, valve, support bracket and flange, pump, valve and component of
any description had been identified and considered into the his calculations .
- Mr. Wakelin assisted Godfreys on behalf of Defendant and he gave detailed evidence on this claim. Mr. Wakelin's was a detailed concise
measured costing and on the balance of probability this evidence can be accepted as indemnity cost for the item.
- Mr. Wakelin had substantial experience in plant and equipment valuation, and he was a reputed Engineer, in the mechanical field, according
to the evidence of Mr. Fair. The extent of his experience is contained in detail in his Statement of Evidence from paragraphs 2-5
of Defendant's Exhibit 8. His CV is Defendant's Exhibit 7 and there was no challenge to his experience or his integrity.
- Mr. Wakelin used experienced Sinclair Knight Merz (SKM) mechanical and electrical staff to undertake the detailed work of assessing
the quantum of the claim. Mr. Wakelin in his evidence said that the SKM staff and sections concerned with the work were very experienced
industrial and electrical engineers, having been involved in the design and construction of many industrial projects.
- So, Mr. Wakelin had employed experienced mechanical and electrical engineers for the initial work. They were sufficiently knowledgeable
for appropriate costing for such work. Mr. Wakelin was cross-examined by the counsel for the Plaintiff, and in the cross-examination
he gave details of the said claim and his involvement and was able to establish the calculations.
- Mr. Wakelin used the following background information to assist the valuation included:
- (i) Edison Consultants as built drawing schedule dated March 2003 for Process industrial, hydraulic service and electrical services
- (ii) Houng Lee Kaba and Partners – floor layout plans February 2003
- (iii) Edison Consultants Fire Damage Assessment Report -Building services and process services
- (iv) Data from Godfreys containing information from a plant valuation schedule by Becas provided by the plaintiff
- The information used by Mr. Wakelin was provided by the Plaintiffs. They were the Plaintiff's documents. Mr. Wakeling gave detailed
description of how he arrived at costing. (See Defendant's Exhibit No. 5 p 78-111 and Exhibit 8 annexed 2).
- This evidence proved the Defendant's adjusted amount on balance of probability. Compared with Mr. Kumar's evidence on the issue Mr.
Wakelin was more methodical and precise. Mr. Fair could not give evidence relating to the amounts in his evidence.
- The adjusted claim for All Services Except Electrical was made up as follows:
D5 page |
| Table Name | Table total | Indemnity Adjustment | |
| Piping |
| | align="tgn="top"> 105 |
| Water Supply | 47,421 | /tr> | 104 |
| Water Supply | | | 103 |
| >Tallow Piping | tom"> 14,907 | | 102 |
| Caustic Soda Piping | 20,368 | | valign="tgn="top"> 101 |
| Soap Piping | 12,934 34 | | < 100 |
| Lye g | 23,3503,350 | | 99 |
| Coconut Oil & Chilled Water piping | 28,068 | | 98 |
| Process water piping | 9,323 | 97 |
| Cooling water piping | 36,453 | | 96 |
| Steam Piping | 52,179 | | valign="tgn="top"> 95 |
| Condensate Piping | 34,5 34,501 | /tr> | 94 |
| essed Air piping | 27,807 | | | Subtotal 1 |
| 322,8b> | #160; | |
| Branch Line allowance at | 24,220 | | | Sul 2 | Total Piping | 090 | |
| Less duplicated items |
| - 7,500 | | 116 |
| Net piping |
| 166,045 | |
| Valves | | | | 105 |
| Valve schedule | 1,33 1,332 | | 104 |
| schedule | 366 | > | 103 |
| Valve schedule om"> 2,788 | | 102 |
| Valve schedule | | 101 |
| Valve schedule | 8,831 | | 100 |
| Valve schedule | 17,733 <733 | | 99 |
| Valve schedule | 2,444 | < | 98 |
| Valve schedule | 1,415 | | 97 |
| >Valve schedule | 1,188 | | 96 |
| Valve schedule | 30,641 | | 95 |
| Valve schedule | 1,947 div> | | align="tgn="top"> 94 |
| Valve sche/div> | 23,040 <040 | | | Subto |
| 95,248 | 47,624 |
| Pumps – repairs |
| | 81 |
| Line items GF D.5.1 - GF C.46 inclusive | 39,658 | Total Laundry Soap adjustment as per Godfrey evidence | 253,327 | - The adjusted claim for the electrical services was made up as follows, the details of which are to be found at pages 82-84 of Defendant's
Exhibit 5.
D5 page | Category | Table Name | Table total | Indemnity | |
|
|
| | < op"> 82-84-84 | Electrical | Replacement Value (Electrical), being all detailed in this scis schedule 275,822 | | | Less design to fees section | - 10,500 | | | Net adjusted electrical services claim as per Godf Godfrey evidence Para 19 | idth=valign="top"> 265,322 | | v> 132,660 | - Considering the evidence of Mr. Wakelin and Mr. Kumar it was evident that Mr. Wakelin had produced a detailed analysis of his costs
for the damage and this proves indemnity value for the item. Mr. Kumar's rounded off figures were not supported by any documentation
and cannot be relied as there was no such detail as to how he arrived at such amounts.
- Even looking at figures in Mr. Kumar's costing, one could easily see all are round figures indicating absence of any detailed costing.
In the circumstances I accept the costing presented by Defendants $253,327.00 and $132,660 as indemnity value for the said items.
Transformer
- The first issue was whether this can be allowed as a loss to the Plaintiffs. According to the Defendants the Plaintiffs could not
prove that there was an insurable interest in the said item in order to claim.
- The Plaintiff could not produce any documentary evidence of actual payment for the purchase of the transfer or even that being considered
as an asset to the Plaintiff in its books of accounts or in its assets register or in the latest valuation of assets before the fire
which was done in 1999 (Becca valuation).
- No evidence was given as to why it was not included in any of these valuations prepared by the Plaintiff, prior to the incident. This
was a vital issue that was not answered by Plaintiffs in evidence. First the Plaintiffs should be able to prove that the transformer
was an asset that belonged to the Plaintiffs that had an insurable interest.
- Nearly after a year from the fire the Plaintiff produced a letter from FEA but lost adjusters for the Defendant was sceptical about
this letter. The letter was provided by the insured from an employee of FEA but this document was not proved by the Plaintiff at
the hearing calling evidence.
- The author of the said letter could not be located by the Defendant to verify the authenticity of the document. This had increased
the speculation on the claim.
- Even at the hearing the Plaintiff did not call the author of the letter to prove it. If the said person cannot be found a fresh letter
from FEA could have obtained from a person who can give evidence in court prior to the assessment. The Plaintiff did not do it and
thus there was no proof of the claim for transformer by the Plaintiff.
- It was common ground that the transformer had been in place for a considerable time, at the location, and may be from the start of
the factory at that site as it may have been a dedicated transformer. There was no evidence produced from FEA, except the said letter,
on this transformer.
- The Plaintiff was unable to produce any documentary proof that the Transformer was considered as their asset. In 1994 (Rolle valuation)
a detailed asset valuation was done and again in 1999 (Beca valuation) there was a valuation of all the assets but the transformer
was not included either the 1994 Rolle valuation, or the 1999 Beca valuation. The Plaintiff needed to explain this omission, and
also the type of interest they had relating to the transformer.
- The Plaintiffs in their written submissions stated that they were unable to prove their insurable interest as the transformer was
installed 30 years ago. (See paragraph 111 of the submission). Even MM components in the toilet soap line were manufactured in 1969
(more than 30 years from fire) and would have been purchased at that time but this did not prevent them being proved as their assets.
So, this argument cannot be accepted as an explanation for not producing proof. In any event, there was no explanation in the evidence
of the nature of the arrangement between FEA and the Plaintiff relating to the said item. This should be available with the Plaintiff
if they had an insurable interest.
- Though a letter was from FEA the Defendant required more details as the author could not be located. Since there was no acceptance
of the said letter the item remained disputed and the assessment needed to be done by the court. So the burden of proof of insurable
interest was with the Plaintiff.
- Mr. D. Lodhia was called to give evidence regarding financial matters but he was unable to explain how the transformer was missing
in their assets registry, or the nature of arrangement of between FEA and Plaintiff relating to said item.
- Mr. Kumar who gave evidence for the Plaintiff referred to said letter from FEA, but again it was hearsay evidence and I am not inclined
to accept it as this fact could have been proved from direct evidence without much effort, but the Plaintiff did not do it.
- Why the Plaintiff did not call evidence from FEA to prove the status of the transformer that got destroyed was not explained. By not
calling FEA the letter of FEA remained not proved to the court, and without that there was no proof of its insurable interest.
- According to the definition of "Insured Property" contained in the Insurance Policy states;
"Tangible property of every description not expressly excluded, the Insured's own or held by the Insured jointly or in trust or on commission or for which the Insured is responsible or has assumed responsibility all while located at any situation or other place anywhere in Fiji or as otherwise."(underling is mine)
- The Plaintiff did not adduce evidence to prove that it owned or 'held by the insured jointly or in trust or on commission for which
insured was responsible'. Such evidence could be proved by calling evidence from FEA. Without calling evidence the Plaintiff cannot
rely on the said definition as there was no proof of the arrangement between FEA and Plaintiff relating to the transformer.
- The Plaintiff in the written submission contended that they were responsible for the transformer, but there was no evidence adduced
at the hearing on balance of probability that they had an insurable interest in it. Such a thing would have adduced by an official
of FEA, but failed to do it.
- If the Plaintiffs were responsible for the transfer, what was the responsibility conferred on them has to be stated clearly. No such
evidence was produced at the hearing. For a thing like transformer which was part of distribution of electricity, and would be part
of the distribution grid of the electricity, hence it was FEA who can give evidence regarding the responsibility of the item and
the insurable interest or any other interest.
- The burden of proof was with the Plaintiff to prove the insurable interest of the transformer but the only evidence was the letter
of FEA. In the analysis of evidence the insurable interest was not proved on balance of probability by the Plaintiff. The said letter
does not indicate how the insurable interest was decided by the signatory to the letter. So an explanation was needed from an authorized
official from FEA.
- Even if I am wrong on the issue of ownership or insurable interest there was no evidence to prove the indemnity value of the transformer
produced at the hearing.
- Again the indemnity value of such a transformer could be adduced from FEA. How old the transformer was and its value at the point
of fire was not established. Whether it was repaired or replaced during, the time of the operation was not revealed.
- The onus of the Plaintiffs did not end at proof of ownership or insurable interest, but the proof of indemnity value for the item
as well. There was no evidence produced at the hearing to ascertain the indemnity value of the transformer. This would have possible
thorough evidence from FEA or another person who had special knowledge of the value of the transformer.
- So, the claim for transformer cannot be granted on two grounds. First, there was no proof of ownership or insurable interest. Second
there was no proof of indemnity value for the item, as no evidence was produced to prove it.
- The claim for Transformer was not allowed for the above reasons. I do not wish to discuss the legal submissions contained in the written
submissions for the Plaintiff on this issue. Without adducing required evidence legal submission cannot prove a fact in the assessment
of evidence.
Additional Electrical Services
- Mr. Wakelin discussed a claim value for $14,642 in additional electrical services costs, which is apparently not added in to the Godfrey's
adjustment. This cost was the result of revised plans sent to Mr. Wakelin, and was described in the summary of changes indemnity
value of 50%, or $7,321 was added accordingly.
- It was also pointed out by Mr. Patel to Mr. Wakelin that the Engineering fees section of Mr. Wakelin's schedule of electrical services
costs - Defendant's Exhibit D5 page 84, totaling $10,500, was missing from the Fees cover in Godfreys' adjustment. This should also be added for engineering fees.
- There is no need to include the above two amounts under contingency as they were specifically identifiable and measurable costs. The
contingency was for unforeseen costs that were missed by the parties.
Item 16 - Personal Effects
- The sum of $1,350 was claimed as employee effects.
- The presented, adjusted and disputed amount for the Personal Effects claim is as follows:
Claim | Adjusted | Dispute | $1,350.00 | Nil | $1350.00 | - The policy provides a cover for personal effects of employees. The covering clause is to be found at Tab 7 at page 11. It says:
"Employees personal effects are deemed to be included in the description of Insured Property as if they were owned by the Insured,
but only whilst the effects are in or about premises owned or occupied by the insured, or elsewhere whilst being worn, kept, carried
or used by employees acting in the course of their employment."
- It is common ground that the personal effects claimed belonged to the Directors of Punjas. The items claimed consisted of a Digital
Camera, a Digital Photo Printer, 10 Musical CDs, a Leather Travelling Pouch, and Miscellaneous Items of card holder, books, framed
pictures, cordless mouse, 3 bottles of black label whiskey, 2 bottles of Absolut Vodka, 1 bottle rum, 1 bottle Gin and 1 bottle of
VAT 9 Whiskey.
- Mr. Lodia gave evidence to the effect that both directors were employees of the Plaintiff and they were in the payroll of the organization,
but he did not bring any documents to prove his contention. This could have easily done by producing relevant pay sheets or other
documents e.g. FNPF numbers etc. In the absence the Plaintiff failed to prove the claim for personal effect on balance of probability.
Building
- There was damage to the building where the plant and machinery were installed. This building was located in a complex of industrial
lay out. The Plaintiff desired commercial value of the building on rental capitalization method. The instructions by the Plaintiffs
were specific for the said valuation. There was no independent judgment of the said valuation by the said entity employed for the
purpose.
- The Plaintiffs did not call the expert who made it to prove it at the hearing.
- There was contrary evidence from another expert report regarding the valuation of the building. Mr. Fair was not the person who made
the valuation. The Plaintiff's valuation report was prepared by Dunlop Stewart and it was disclosed to the Defendant one month before
the commencement of this assessment hearing but again they did not opt to call an expert to prove it. The Plaintiffs already knew
the expert valuation of the Defendant by this time. So, long before this valuation the Plaintiffs were aware of the Defendant's exert
report on valuation, yet decided not to prove their valuation at hearing.
- The Defendant produced a valuation and also called the expert to give evidence.
- The Defendants rejected the rental capitalisation method, which works by allocating an annual rate per metre of floor area, then capitalising
the rental at a suitable rate adopted by the Plaintiffs' valuation.
- The building had no real rental, and it was not possible to identify a rental value for this building alone considering the location.
This was located in coastal area inside industrial site. The building was one of the closely integrated one on an industrial site
which shared lot of amenities. The buildings were located very close, so it was not clear whether one building could be isolated
and rented in terms of local laws and regulations.
- The rental of the whole industrial site would have been a better option if the rental capitalization method was adopted, but then
the rental for said building should be appropriately factored for the valuation. Even this would not be the best method for considering
indemnity value for the said building.
- The value arrived by the rental capitalization for the building destroyed was artificial, and also unrealistic. No evidence was produced
as to the adoption of this method when there was no separate existence of the said building from the closely integrated manner in
which they were situated. The electricity and other amenities had to be shared with the industrial site and there was no separate
entrance or access to this building though it was situated next to a main road. So, if this was going to be rented first it should
have necessary access and whether that would conform to local government regulations were not discussed in the report.
- At the same time sharing electricity from a transformer that supplied to an industrial site will also have to be considered. The corruption
of electricity wave from such heavy machinery needed to be considered as the tenants might have to use some additional safeguards
for the electricity supply from power fluctuations as well as other effects from such an industrial location. The noise, odour, smoke
and other factors like constant movements of men and material would also be considered by any prospective tenant. These factors would
affect rentals and commercial market rentals for the area cannot be applied without suitable correction. It should also be noted
that without this building the soap making industry could not function and considering the closely integration the renting of the
building was unrealistic and hypothetical.
- The above factors were not considered in the Dunlop Stewart valuation. Considering all the factors there was any other in fact this
hypothetical approach simply shows that the rental capitalisation method had its limits, as in this case.
- Mr. Horsely supported the Defendant's position in rejecting the valuation by Dunlop Stewart. Mr. Horsely in referring to the Dunlop
Stewart Valuation at paragraphs 28 to 30 said:
29.They were wrong to approach their market value of the single building when it was integral to the business operating across the
entirety of the site and that as a stand-alone building in the words of the Public Works Act 1981the part is (was) of a size, shape,
or nature for which there is no general demand or market.
30.Put simply were they to have undertaken a market value approach to the assessment of indemnity Dunlop Stewart should have valued
the entire property before the loss and again after the event where the loss suffered would have been the difference between the
two valuations.
- Mr. Horsely gave evidence in support of his contention and he was cross examined by the counsel for the Plaintiffs. Mr. Godfrey used
the replacement less depreciation method to arrive at the adjusted indemnity value of $367,752.00. The building's main purpose was
to protect the industrial plant within it. Mr. Godfrey evidence, supported by Mr. Horsely was that plants were frequently valued
on this basis, and there was no reason the building cannot be also valued this way to accurately represent its remaining life.
- In determining the indemnity, the Defendants instructed Rawlinson Jenkins to measure indemnity value of the building as it was, but
new. The replacement cost was established from Rawlinson Jenkins Fiji: pages 122-123 of Defendant's Exhibit 5. Godfreys then adjusted
this costing - Defendant's Exhibit 5 at Page 121 - to exclude items not relevant to the building before adding back margin and preliminaries,
which are percentage costs. Godfreys then applied depreciation at 2.75% on a diminishing value basis.
- The Defendant calculated the resulting replacement cost as $945,362, and indemnity value $367,752. The adjusted building claim of
the Defendant was as follows: - Defendant's Exhibit 5 at page 121 –
Indemnity adjustment on building | | | | Rawlinson & Jenkins costing |
|
|
|
| | > Total Cost |
|
| 1,112,392 |
|
|
| | less |
|
|
|
|
| | Less VAT |
|
| -123,599 |
|
|
| | | idth="41" vali valign="bottom">
| 988,793 |
|
|
| | Preliminaries |
| | -65,604 div> |
|
|
| | |
| 923,189 |
| <
|
| | Contingency |
| width="73" valign="bottom"> -50,000 div> |
|
|
| | | 53,139 | 873,189 | width="67" valign="bottom">
|
| | margin |
|
| -53,/div> |
|
|
| | |
|
|
|
|
| | Heating and ventilation | in plant | -22,500 |
|
|
| | Electrical services | | | idth="41" vali valign="bottom">
| 785,750 |
|
|
| | Plus Margin |
| 6% 47,145 ,145 |
|
|
| |
|
| 832,895 |
|
|
| Plus preliminaries | 7.5% | 62,467 |
|
|
| | Plus Contingency |
| 50,000 |
|
| | |
|
| 945,362v> | Depreciated at 2.75% of diminishing hing value |
|
| On a sectional agis | | |
| Final cost > | 945,362 |
|
|
| | > |
|
|
| Value | Residual
| | |
|
|
| /td> | Depn rate /div> | 2.75% | | < Built: | Life |
| width="77" valign="bottom">tom"> Formula Cost | Section ppn |
| | 1950 | 60 | 53 | 30.7% | 251,141 | 25.4% | 0.23092 | 57,992 | 1965 | 60 | 38 | 37.4% | 305,644 | 30.9% | 0.34688 | 106,022 | 1970 | 60 | 33 | 31.8% | 259,750 | 26.2% | 0.39727 | 103,192 | 1995 | 60 | 8 | Blg rate | 128,449 | 17.5% | .78277 | 100,546 | | < | | |
|
|
|
|
|
|
| | - Mr. Horsely stated that a market value could not be ascribed to a distinct asset that had no market on its own and supported the decision
to find the indemnity value of the building using the replacement less depreciation. I accept Mr. Horsely's evidence and the valuation
based on depreciation method, as the building had no separate existence and heavily depended on the site.
- Mr. Horsely also confirmed that the rates of depreciation used by Godfreys at 2.75% per annum on diminishing value of the elemental
components of the building were reasonable in the circumstances of an industrial building located in a Pacific Island location.
- Mr. Horsely however opined that Godfreys should have included for costs that were excluded from Rawlinsons elemental analysis such
as professional fees, permit costs etc. Mr. Horsely suggested a high percentage of 12% to the replacement cost increasing the sum
to $1,058,805 and a resulting depreciated replacement cost of $411,875.
Punjas Charity Trust – Stock $49,803 & Loss of turnover - $23,394
225. This claim raises the question of interpretation of the policy wording in the context of the surrounding circumstances. Punjas
Charity Trust carried on the business of manufacturing candles and incense sticks using machinery owned by the insured, Ocean Soaps
Ltd, from the Ocean Soap factory destroyed by the fire. Its products were distributed by insured. The Defendant was aware of this
operation by as admitted by Mr Godfrey in cross examination.
226. The Defendant was aware of the risks associated with such venture and if they did not make provision for the risk it was their
fault. The word "Business" was defined in the policy at p.4 Tab 7 as "all businesses of whatsoever kind conducted by the insured"
and includes "soap & allied products" and "religious organisation" and Punjas Charity Trust was the only religious organization carrying on business at that industrial site. So the intention of the
parties was clear to include said religious trust under the insurance cover. If not the word 'religious organization' had no meaning.
227. A trustee was entitled to insure trust property in the trustee's name according to s.42(1) Trustee Act (Cap.65) which states as follows:
42.-(1) A trustee may insure against loss or damage, whether by fire or otherwise, any insurable property to any amount, including
the amount of any insurance already in being, not exceeding the full replacement value of the property; and may also insure against
any risk or liability against which it would be prudent for a person to insure, if he were acting for himself; and may pay the premiums
for such insurance out of the income of the property concerned or out of the income of any other property subject to the same trusts,
without obtaining the consent of any person who may be entitled wholly or partly to that income.
228. In Lucena v Craufurd [1806] EngR 12; (1806) 127 ER 630 Lord Eldon said at p.651: "A trustee has a legal interest in the thing and may therefore insure". The "Insured" named in the policy were several companies, individuals and trusts "and all subsidiary companies or any of them for their respective rights and interests".
229. The words contained in the Insurance Policy "......or any of them for their respective rights and interests" refer to each named insured or only to the subsidiary companies or any of them. This will invariably include the said religious
trust.
230. The words "for their respective rights and interests" are commonly used to describe a composite insurance policy. Mr Godfrey did not say in his evidence that he had considered whether
the policy was a composite policy or that he had considered the meaning of the words "for their respective rights and interests" in the context of a composite policy. He clearly did not. Had he done so, he would not have said the wording was 'unusual'. Even
assuming that it was unusual it was the Insurance Policy that they accepted premiums for number of years. By conduct the Defendants
have accepted the said wordings and the meaning attached to it.
231. In General Accident Fire and Life Assurance Corporation Ltd v Midland Bank Ltd (1940) 2 KB 388 the English Court of Appeal had to deal with the phrase "for the respective rights and interests" in the context of whether the policy was a joint policy or a composite policy. Sir Wilfred Greene MR said:
At page 404-405:
"That there can be a joint insurance by persons having a joint interest is, of course, manifest. If A and B are joint owners of property
— and I use that phrase in the strict sense—an undertaking to indemnify them jointly is a true contract of indemnity
in respect of a joint loss which they have jointly suffered. Again, there can be no objection to combining in one insurance a number
of persons having different interests in the subject-matter of the insurance, but I find myself unable to see how an insurance of
that character can be called a joint insurance. In such a case the interest of each of the insured is different. The amount of his
loss, if the subject-matter of the insurance is destroyed or damaged, depends on the nature of his interest, and the covenant of
indemnity which the policy gives must, in such a case, necessarily operate as a covenant to indemnify in respect of each individual
different loss which the various persons named may suffer. In such a case there is no joint element at all."
Later on at p.405:
".....................Such a policy, in my judgment, may be more accurately described as a composite policy, because it comprises,
for reasons of obvious convenience, in one piece of paper the interests of a number of persons whose connection with the subject-matter
of the insurance makes it natural and reasonable that the whole matter should be dealt with in one policy. ........"
And at page 406:
"The description of the insured by name, followed by the words, "for their respective rights and interests," in my judgment, read
in its natural sense, indicates that these three persons, having interests which it is not material to investigate for the purpose
of the document, are minded to combine in one policy and each of them to obtain cover from the underwriters in respect of his right
or interest, what-ever it may be — and it may vary from time to time....................."
232. In considering the meaning of the phrase "for the respective rights and interests" the Master of the Rolls in General Accident Fire & Life (supra) said:
At p.406:
"But, of course, the document must be construed as a whole, and what seems to me to be the meaning of that phrase might have to yield
to other indications in the document if that were necessary to produce a proper and fair construction of it."
And at page 408:
"The printed words "the insured" must be construed and qualified by the words "for their respective rights and interests," and those
printed words must be given a construction which will fit in with the essential nature of the contract which is being undertaken."
And at Page: 409:
"The true construction of the words again, in my judgment, must be moulded by reference to the governing phrase "for their respective
rights and interests" and given a businesslike effect in consequence".
233. Mr. Godfrey stated his evidence in his reasoning as follows in his written statement of evidence:
"129. If the Punja Charity Trust is insured solely because Mr Jagdish (Jagjiwan) Punja is insured, then by implication, every interest
of his or any named insured, of any nature would be insured. The insurance market would not accept insurance proposals on these terms
as it would not be able to identify and measure in any meaningful way what it was insuring, and it is fundamental to an insurance
policy that that the subject matter of the policy is identifiable by all parties.
130. I add that Mr Jagdish (Jagjiwan) Punja is most likely to hold his own insurances for other property. The error in this case
is that, having gone to such trouble to specify every party whose interests it intended to insure, the insured did not name this
one."
234. The subject matter of the policy included the business of manufacturing candles and incense sticks, for charity, inside the soap
factory and the risks associated with it. It was not totally alien to the industry as the by produces were used for the said industry,
and this kind of business integration was not an uncommon thing, and importantly the Defendants were aware of it.
235. The Defendant was aware of that business and risk because it knew such manufacturing was being done on the premises and the reason
for including a religious body in the Insurance Policy was to extend the cover to said activity and machinery involved in it.
236. The Defendant agreed to the definition of business stated in the policy which included soap and allied products and religious
organization. If the Defendant was not aware of the said Punjas Charity Trust, why did it include a 'religious organization' under
the 'Business' in the Insurance Policy. It was the only religious organization that functioned on business at the industrial site.
237. In Norwich Union Fire Ins. Society Ltd. v. Traynor [1972] NZLR 504 (C.A.) Woodhouse J said at 509 line 28:
"There is no general rule that an insured is under an obligation to disclose the precise nature or extent of his interest in the property".
238. Earlier Bowen LJ had said in Castellain v Preston [1883] UKLawRpKQB 69; (1883) 11 QBD 380 at 398:
"It is well known in marine and in fire insurances that a person who has a limited interest may insure nevertheless on the total value
of the subject-matter of the insurance, and he may recover the whole value, subject to these two provisions; first of all, the form
of his policy must be such as to enable him to recover the total value, because the assured may so limit himself by the way in which
he insures as not really to insure the whole value of the subject-matter; and secondly, he must intend to insure the whole value
at the time. When the insurance is effected he cannot recover the entire value unless he has intended to insure the entire value.
A person with a limited interest may insure either for himself and to cover his own interest only, or he may insure so as to cover
not merely his own limited interest, but the interest of all others who are interested in the property. It is a question of fact
what is his intention when he obtains the policy. But he can only hold for so much as he has intended to insure.
........
. . . let us turn to the case of a mortgagee. If he has the legal ownership, he is entitled to insure for the whole value, but even
supposing he is not entitled to the legal ownership he is entitled to insure prima facie for all. If he intends to cover only his
mortgage and is only insuring his own interest, he can only in the event of a loss hold the amount to which he has been damnified.
If he has intended to cover other persons beside himself, he can hold the surplus for those whom he has intended to cover" (ibid,
398-399)."
239. In the Insurance Policy, Mr Jagjiwan Punja "for his respective rights and interests" meant rights and interests of his own and as trustee of Punjas Charity Trust. He had an insurable interest in the property and business
of Punjas Charity Trust as a trustee. As such he also had "relation to or concern in the subject matter of the insurance", of Punjas
Charity Trust, namely, in its business of manufacturing candles and incense sticks, and it was permanently situated at the same place
of business that was insured as a 'religious organization'.
240. In the definition of 'Business' for the business interruption claims the manufacture of ' incense sticks' was specifically included
though candles were not included in the said definition. But it can be considered as 'allied product' of soap industry. So for the
business interruption the Punjas Charity Trust operations were included. This supports that the material damage also covered though
not specifically mentioned by its name. It was common ground that the machinery used for Punjas Charity Trust was situated at the
site destroyed by the fire and the amount of damage was not disputed. In the light of that in my judgment the said claim of Punjas
Charity Trust should be allowed as an insured item under the Insurance Policy.
241. The next issue was the proof of the damage to said entity on indemnity basis. The Defendant did not dispute the amounts $49,803 for the stock that was destroyed and $23,394 for the business interruption. So I allow the said claims.
Interest
242. The Plaintiff seeks interest on a compounded basis. It claims compounded interest pursuant to Regulation 2(3) of the Insurance
Law Reform (Interest Rates) Regulations 2004.
- It is the Defendant's position that Regulation 2(3) of the Insurance Law Reform (Interest Rates) Regulations 2004 is ultra vires Section
34 of the Insurance Law Reform Act, 1996.
- Section 34 of the Insurance Law Reform Act 1996 provides as follows:
PART VII – INTEREST AND REGULATIONS
Interest on claims
34. (1) Where an insurer is liable to pay to a person an amount under a contract of insurance or under this Act in relation to a contract
of insurance, the insurer is also liable to pay interest on the amount to that person in accordance with this Section.
(2) The period in respect of which interest is payable is the period commencing on the day as from which it was unreasonable for the
insurer to have withheld payment of the amount and ending on whichever is earlier of the following days:
(a) the day on which the payment is made; (b) the day on which the payment is sent by post to the person to whom it is payable. (3) The rate at which interest is payable in respect of a day included in the period referred to in sub-section (2) is the rate that
is prescribed by regulation.
- Regulation 2(3) of the Insurance Law Reform (Interest Rates) Regulations 2004 says:
(3) The interest accrued to the end of each calendar month is to be added to the amount on which interest is payable under section
34(1) of the Act and bears interest from the first day of the next succeeding calendar month.
246. In terms of Section 34(3) of the Insurance Law Reform Act 1996, the regulation needs to be made to determine the rate of interest. The Regulation 2(1) of the Insurance Law Reform (Interest Rates)
Regulations 2004 dealt with the interest rate and it was 10% P.A. The said regulation not only dealt the issue of interest but also
stated that it should be monthly compounded interest (see Regulation 2(3) of the Insurance Law Reform (Interest Rates) Regulations
2004). So obviously this was not a matter that was delegated for making of the regulations.
247. A statutory regulation must be "within the four corners of" of the statute (see Carltona Ltd v Commissioners of Works [1943] 2 All ER 560 (CA) at 564 per Lord Greene MR. It should also be "capable of being related to" the main statue. (see A-G (Canada) v Hallet & Carey Ltd [1952] AC 427 (PC) at 450 per Lord Radcliffe), the powers of legislation so delegated.
- In McEldowney v Forde [1971] AC 632 (HL) at 658(E-F), Lord Diplock laid down a three-step test for the courts:
"First, to determine the meaning of the words used in the Act of Parliament itself to describe the subordinate legislation which that
authority is authorised to make, secondly, to determine the meaning of the subordinate legislation itself and finally to decide whether
the subordinate legislation complies with that description."
- In Carroll v Attorney-General [1933] NZGazLawRp 163; [1933] NZLR 1461 (CA) at 1478, Ostler J stated:
"The principles upon which the Court determines the validity of regulations made by Order in Council are well settled ... [The Courts]
merely construe the Act under which the regulation purports to be made giving the statute ... such fair, large and liberal interpretation
as will best attain its objects. Then they look at the regulation complained of. If it is within the objects and intention of the
Act, it is valid. If not, however reasonable it may appear, or however necessary it may be considered, it is ultra vires and void
... The objects and intention of the Act can, of course, be gathered only from the words used."
- Section 34(1) of the Act imposes on insurance companies a duty to pay interest on unpaid amounts owing under contracts of insurance.
Section 34(2) prescribes the period for which interest is to be paid, and section 34(3) prescribes the rate of interest as fixed
by regulations made under section 35.
- The Defendant accepted that the rate of interest prescribed by Regulation 2(1) of the Insurance Law Reform (Interest Rates) Regulations
2004 interest rate of 10% per annum. It should not be compounded as the Insurance Law Reform Act 1996 does not speak about a compound interest. So the issue of compounding it monthly will not arise as stated in the said Regulation.
- The scope of the Regulations made in terms of Section 35 of the Insurance Law Reform Act 1996 cannot be more that was prescribed in terms of Section 34(2) of Insurance Law Reform Act 1996. In the absence of any provision making the interest a compounded one in the Insurance Law Reform Act 1996, the regulation cannot change it to the compounded one.
- The next issue is when the interest rate of 10% starts to accrue under Section 34(2) of the Act. The Section 34 (2) states:
(2) The period in respect of which interest is payable is the period commencing on the day as from which it was unreasonable for the insurer
to have withheld payment of the amount and ending on whichever is earlier of the following days:
(a) the day on which the payment is made; (b) the day on which the payment is sent by post to the person to whom it is payable. - In Bankstown Football Club v CIC Insurance Ltd (Unreported, Supreme Court of New South Wales, Coles J, decided on 17 December 1993) the Supreme Court of New South Wales held that
the date on which the interest starts to accrue must be determined objectively when discussing the principles to applied when considering
"the day as from which it was unreasonable for the insurer to have withheld payment of the amount..." under Section 57 of the Insurance
Contracts Act, 1984. Section 34 of the Insurance Law Reform Act, 1996 has exactly the same wording as Section 57 of Australian Insurance Contract Act, 1984.
- In Sayseng v Kellogg Superannuation Pty Ltd [2007] NSWSC 857, Nicholas J observed At paragraph [7]
"In my opinion it should now be accepted that the correct approach to be taken by the court on this question is that taken by Cole,
J in Bankstown Football Club. In my assessment, the cases to which I have referred establish that the question of reasonableness is to be judged by reference to the true position in respect of the claim with allowance to be made for the insurer to have a reasonable period of time within which to investigate the claim and to consider its position. The discretionary determination is to be made having regard to the particular circumstances of the case, including the probable
issues which require investigation. Under the Act the court is not required to evaluate and pronounce upon the opinion or decision-making process of the insurer. It is not relevant that the insurer acted bona fide in denying the claim, or when the judgment of the court established the insurer's
liability to pay it. In short, the award will be calculated on the basis of what the court finds is a reasonable time for completion
of the insurer's investigation of the claim. Put another way, in my opinion, the insurer is not automatically liable to pay interest from the day on which it became liable to
pay to a person an amount under a contract of insurance. Under s.57 12) liability to pay interest is to be calculated with regard to the day on which it was unreasonable for the insurer to
withhold payment of the amount after it had become liable to pay it in response to a claim."
- The Insurance Policy contained two distinct parts under which the claims were made. They were MD and BI. The BI claim was by its
nature, a loss that occurs over time, not on the date of the fire, but the insurance policy did not make a distinction of the two
types of claims as regards to the interest.
- All the claims should be settled as soon as possible and if not interest should be applied to assessed amount considering the circumstances
of the case. This case involved a substantial claim. First the Defendants imposed the restriction applicable stating that the fire
was caused by a malicious act of the Plaintiffs, but was not successful. Considering the circumstances of the case, both parties
had resorted to ascertain the loss through the engagement of professionals in the insurance industry. So a claim preparer and lost
adjuster were employed by respective parties to the action. This process could not resolve the main issues between the parties relating
to the substantial claims, but some claims were resolved. Even at the hearing of the assessment Plaintiff could not prove on the
balance of probability main disputed claims.
- The court needed to calculate the interest from 'the day as from which it was unreasonable for the insurer to have withheld payment.' As submitted by the Defendant in their written submission, the guiding principle was the reasonableness in the refusal to pay what
was due to the Plaintiffs. Considering the circumstances of the case in my judgement that interest should accrue from the date of
determination of liability in this action.
- Generally, assessment of liability and assessment of damages would not be separated and would be decided simultaneously. By adopting
to have a split trial, this advantage should not be denied to the Plaintiff. After the determination of liability there was no application
of malicious act restriction.
- According to the Section 34 of the Insurance Law Reform Act 1996, there was no distinction of type of claim contained in a policy the interest rate 10% was applicable to entire amount from the date
of determination of liability. (i.e from 6 May 2011) It should be noted that the Plaintiff had received as part payments 3.75 million
prior to that date and this sum should be deducted from the total assessed damage for the application of interest.
- It should also be noted long before this date the parties have tried to settle the claims and had also agreed certain claims, but
no payments regarding the said claims were settled by the Defendant. So the Defendant had unreasonably held claims due to the Plaintiff
for a considerable time period. It was not my duty to evaluate the insurance claim payment process, but the time taken was too long
and the Defendant had stopped the process of engaging professionals. There was no communication produced in the court indicating
termination of the engagement of lost adjuster to the Plaintiff. This behaviour also supports unreasonable for the Plaintiffs to
recover their claims for the loss early.
- In my judgment the date of interest should be from 6th May, 2011 for the reminder of entire claim till it is fully paid (or if paid
by post when posted such payment).
- The policy has at page 28 (Folder 2, Tab 7) it states:
"In the event of loss or damage giving rise to a claim under this Policy, the Company will make progress claim payments on production of acceptable evidence of insured loss.
"Provided that, if the aggregate of progress payments exceeds the total amount of the adjusted loss, the Insured will immediately
refund the difference between the amount of adjusted loss and the aggregate of payments actually made."(emphasis added)
- The Defendant contends that the above clause contemplates that payments were to be made in the aggregate, not against specific items.
I do not agree. If so why did they pay a part payment? The test was reasonableness of the non payment of Defendant for the claims
already settled between the parties. There was nothing preventing them paying the amount according to their adjustments, leaving
disputed amount to be settled through other means including litigation.
- The Insurance Policy at the beginning stated that each party has to be considered separately.(see page 2 of the Insurance Policy).
So claims needed to be considered separately and the aggregate of claims can be paid till the determination of the rest through ADR,
or by a civil action.
- While considering when any payment was due, under cross examination Mr Daniel Yee, the insured's broker said that in his experience,
insurance companies pay within weeks. This was a more generalized statement. However in cross examination he accepted that he was
dealing in a fire claim that was still under investigation after six months.
- The policy has (page 21 – CLAIMS conditions, Section 2 (d)) a requirement that the Insured produce such records:
Upon becoming aware of the happening of any Damage, the Insured must –
(a) immediately notify the Company, (b) use due diligence and do and concur in doing all things reasonably practicable to minimise any interruption of or interference
with the Business and to avoid or diminish the loss; (c) as soon as is practicable, deliver to the Company a statement in writing of any claim certified by the Accountant, whose reasonable
fee will be paid by the Company, with all particulars and details reasonably practicable of the loss; (d) produce and furnish all books of account and other business books, invoices, vouchers and other documents, proofs, information,
explanations and other evidence and facilities as may reasonably be required and verification of the claim and, if required, a statutory
declaration in verification of the particulars. The term "Accountant" under this condition means an accountant or adjuster whose qualifications are acceptable to both the Company
and the Insured, and is appointed by both the Company and the Insured.
- The Defendants contended that, that any payment was due prior to the submission of investigation records in October, 2004. I do not
need to consider this argument as I have awarded interest from 2011, that was nearly 7 years after said submissions of the records.
Business Interruption (BI) Claim
- The above mentioned claim was different from the other claims on number of ways. First, it was not to be assessed on indemnity basis
as on Material Damage. The other important feature was that it was on full value basis, for future loss of business after the event,
and the limits were specifically mentioned. For the claim preparation a cost of maximum 200,000 was allowed and additional expenditure
was limited to 500,000 for any one event, was allowed under BI.
- Both parties have adjusted the BI claim to arrive at 1,991,358. In Mr. Fair's evidence one remaining issue was the additional costs
incurred by MSM Loss Management Limited, in attending a meeting with the Defendants due to the non availability of the Plaintiffs
directors at that meeting. This was requested by the Defendants, but from the evidence it was on behalf of the Plaintiff that they
had attended. If the MSM Loss Management wanted their fee for attendance being paid by the Defendant, they should have indicated
that to them before the meeting as they were retained by the Plaintiffs and not by the Defendant.
- I have included Punjas Charity Trust under the Insurance Policy hence 23,394 was the loss turnover from that should be allowed.
- If there was an outstanding issue of payment at that time it would have been informed, and resolved at that time. Before attending
the meeting MSM Loss Management would have obtained some authority from their clients the Plaintiffs and they had appeared on behalf
of the Plaintiff as their representatives. So I do not allow that expenditure.
- There was an addition claim of Increased Cost of Working (ICW) claimed by the Plaintiff under BI, for a sum of $44,973. This was not
proved at hearing by the Plaintiff (see Tab 13 & 14 of folder 2).
- If VAT is applicable for BI and MD claims that should also be paid by the Defendant. I can't see applicable VAT exceeding the limits
for BI or MD, but for completeness these should be limited for said limitation.
Breach of Contract
- The Plaintiff also claims for breach of contract. The Plaintiffs state that there was an unreasonable delay in admitting liability
under the policy and making progress payments under the policy. The Plaintiff also states that the invoking of malicious damage limitation
was also a breach of contract.
- The Plaintiffs action was based on a report prepared by insurance investigator employed by them. If they did not resort to malicious
damage exception there would have been a danger of reinsurers refusing to pay the claims. The actions of the Defendant to apply the
exception and limit the liability, cannot be considered unreasonable.
- The Plaintiffs soap factory got destroyed and progressive payments were paid in the following manner(see Tab 3 of the Plaintiffs Folder
2)
Date Amount
19/6/2003 - 1,000,000
4/7/2003 - 500.000
11/4/2003 - 500,000
28/8/2003 - 1,000,000
24/11/2003 - 250,000
20/5/2004 - 500,000
Total 3,750,000
- The Defendant had paid a sum of 3.75 million in progressive payments by 20th May, 2004. So progressive payments of over 3 million
were paid to the Plaintiff within one year of the destruction. Considering the nature of the claim and the manner in which the proof
of the damage I cannot say that there was a breach of contract due to delay in payment or resorting to malicious damage limitation.
Final Calculations
Item | Description | Plaintiff's claim | Defendant's position | The final assessment by Court | 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 | Office/Laboratory Minor Lines Toilet Soap Laundry Soap Other Areas Consumable Stocks Demolition Contingency – General Professional fees Europe Trip MM Costs Computer Allowances Salvage All services except Electrical Electrical Services Personal Effects Building Stock Amounts that were needed to add (see paragraph 200, 201 of the Decision) Electricals Engineering Fees Deductible | 178,031 35,138 1,424,235 318,534 163,614 16,797 50,000 Incl. 149,807 30,000 30,000 Incl. 0 317,677 397,875 1,350 650,000 1,091,517 (10,000) | 178,031 30,830 855,764 237,019 155,729 16,797 31,111 30,000 153,325 30,000 30,000 15,500 (30,000) 253,327 132,660 0 367,752 1,041,714 (10,000) | 178,031 30,830 855,764 237,019 155,729 16,797 31,111 30,000 153,325 30,000 30,000 15,500 - 253,327 132,660 - 411,875 1,041,714+49.803* 7,321 10,500 (10,000) |
| 4,844,575 | 3,519,559 | 3,661,306 | Business Interruption | 2,069,675 | 1,991,358 | 1,991,358+23,394* |
| Total Less part payments by Defendants | 6,914,250 | 5,510,917 | 5,676,058 (3,750,000) | *Punjas Charity Trust
Costs
- Both parties were successful to some extent at this hearing. Considering the circumstances in my judgment each party should bear their
own cost.
- For avoidance of any doubt this decision should be considered as a decision of the Master on assessment of damages as agreed by all
the parties at the continuation of the assessment before me on 2nd April, 2013.
FINAL ORDER
- The Defendant to pay the Plaintiffs a sum of 1,926,058 and interest at the rate of 10% P.A from 6th May, 2011.
- Applicable VAT for (a) should be paid by the Defendant for the above sum.
- Considering the circumstances of the case I will not grant costs. Each party to bear their own costs.
Dated at Suva this 24th day of March 2016
Justice Deepthi Amaratunga High Court, Suva
[1] Cross on Evidence (NZ)/Evidence Act 2006/EVIDENCE ACT 20rt 3 Trial process EVA 92VA 92.5
[2] Browne v Dunn (189R 67 (HL); R v Hart (1932) 23 Cr App R 202, applied in R v Auckram (CA 282/07, 12 Decemberember 2007); [2007] NZCA 570 (BC200763296); Transport Ministry v Garry [1973] 1 NZLR 120. See also Perry v R (1982) 150 CLR 580. R v Manunta [1989] SASC 1628; (1990) 54 SASR 17 contains a survey of the "rule in Browne v Dunn". See also Goldberg J's discussion in White v Flower and Hart [1998] FCA 806; (1998) 156 ALR 169 (FCA).The reasoning in R v Hart could not apply to an accused whose defence is an outright denial, and the prosecution has no duty to afford
such an accused further opportunity to establish his credibility: Crime Appeal (CA 273/91) (CA 273/91, 20 December 1991). See also
R v Dewar (CA 547/07, 5 September 2008); [2008] NZCA 344. Mahoney [2004] NZ Law Review 313 argued against a comprehensive duty to put the case. For a helpful review of the common law authorities see Kennedy v Kennedy [2007] DCR 507 (BC200760112).
[3] Browne v Dunn (1893) 6 R 67 (HL), 76-77 (unless the witness has had notice of non-acceptance beforehand, or the story is itself of an incredible
or romancing character). See O'Connell v Adams [1973] RTR 150, 154. Notice may have been given by the conduct of the trial, in which event there is no obligation to cross-examine: Hewinson v
Police [1987] NZHC 64; (1987) 3 CRNZ 27. It is not ordinarily necessary to put to a party matters which are clearly at issue: Stern v National Australia Bank Ltd [2000] FCA 294; (2000) 171 ALR 192 (FCA). The mere exchange of briefs does not, without more, amount to "full notice beforehand": Pain Management Systems v McCallum (2002) 16 PRNZ 227, 258 per Penlington J.
[4] Reid v Kerr (1974) 9 SASR 367; R v Byczko (No 2) (1977) 17 SASR 460; and see discussion by Bray J in Thomas v van den Yssel (1976) 14 SASR 205 and, particularly, Allied Pastoral Holdings Pty Ltd v Commissioner of Taxation [1983] 1 NSWLR 1, 16, per Hunt J. See also R v Webber [2004] UKHL 1; [2004] 1 All ER 770 (HL), 785 ("where counsel is instructed to put a positive case").
[5] See Phipson, Law of Evidence, 14th ed, para 12-13. [6]R v Fenlon (1980) 71 Cr App R 307, 313 (no different rule as to defendants between themselves).
PacLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.paclii.org/fj/cases/FJHC/2016/224.html
|