|
Home
| Databases
| WorldLII
| Search
| Feedback
High Court of Fiji |
IN THE HIGH COURT OF FIJI
AT LAUTOKA
CIVIL JURISDICTION
HBC 191 OF 2020
BETWEEN:
RAVINESH CHAND T/A RISH DISTRIBUTORS of Vatiyaka, Ba, Businessman.
PLAINTIFF
A N D:
MANOJ KUMAR T/A EKTA BUILDERS a duly incorporated company having its registered
office at Link Road, Lautoka.
DEFENDANT
Appearances: Ms. Ben S. for the Plaintiff
N/A for the Defendant
Date of Hearing: 28 August 2023
Date of Ruling: 29 January 2026
R U L I N G
| (a) | on 14 May 2018, Chand and Manoj Kumar (“Kumar”) the defendant, entered into a building contract. |
| (b) | Kumar was to build a two-flat single storey house at Namosau in Ba. |
| | The value of the contract was $120,000 – 00[1]. |
| (c) | the Agreement sets forth a payment plan which is structured as follows[2]: (i) $36,000 to be paid upfront upon temporary power and water supply, job set out, trench works, steel works, floor works and block work up to five rows. (ii) $35,000 to be paid upon completion of block work up to beam height, roofing structure, plumbing works, doors and windows, electrical works. (iii) $35,000 to be paid upon completion of joinery works, plaster works, painting, tiling works, sewer line works and interior finishing. (iv) $14,000 to be paid upon grant of Engineer’s Certificate. |
| (d) | Chand actually paid Kumar $114,000 out of the total contract price[3]. He only withheld $6,000. This was to be paid upon final completion when the completion certificate is issued. |
| (e) | however, Kumar left the job site on 16 January 2020 without completing the contract. He did not tell Chand why. |
| (f) | Chand sent formal demands to Kumar to return the money for work not completed. |
| (g) | according to Chand, Kumar only completed the first phase of the building. He neglected to build the second and third phases. An undated
defect Report prepared by Vinadu Construction states that, following inspection, “three-quarters of second stage was left and
stages three and four were completely left” (sic). The estimated full labour costs to complete the job is stated as $25,000. |
| (h) | Chand had to hire another contractor (namely one Munesh Rajend trading as Vinadu Construction) to complete the house. He incurred
an additional charges and costs, $25,000 for labour and $52,5337 for materials. |
| (a) | $74,000 being the advance paid by Chand to Kumar in respect of Phases 2 and 3 of the project, which Kumar failed to complete. |
| (b) | general damages. |
| (c) | interest |
| (d) | costs |
....................................
Anare Tuilevuka
JUDGE
29 January 2026
PacLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.paclii.org/fj/cases/FJHC/2026/31.html